*DDC inspected the ongoing work of Teaching hospital and GMC Doda* _Directs the executing agencies to speed up the work and complete the projects under fixed timeline_
Publish Date : 07/02/2020
DODA, February 05:
District Development Commissioner Doda Dr Sagar D Doifode today visited the District Hospital Doda and Ghat to inspect the ongoing work of Teaching hospital near DH Doda and GMC Ghat.
During the inspection DDC was accompanied by the SSP Doda Mumtaz Ahmed,SP Operations Doda R P Singh,Ex En PWD, Adminstrative officer GMC Doda,MS District Hospital Doda besides by the official of executing agencies and district administration.
The DDC was informed that the foundation of the teaching hospital has been completed and errection of the column structure has been started.
In this regard DDC has directed the executing agencies to draft a pert chart and fixed the timeline so that the whole structure shall be completed by the end of June 2020.
Later DDC visited Ghat and inspected the ongoing work of GMC Doda,the DDC was apprised that block masonry work has been completed in the main block of the
GMC and plastering work is on completion stage.
Ex Ex PWD also informed the DDC that the structure of 3 lecture halls are completed and construction of boys hostel in on completion stage, besides construction of boundary wall is ongoing.
DDC said that though progress has increased from the last few months but more progress has to be achieved and directed the executing agencies to expedite the work and complete the construction under the fixed timeline.
DDC has directed the executing agencies to work on double shifts and increase the number of skilled labourers to meet out the timelines, besides he asked the concerned to fixed the timeline to the contracting agency in compartment manner and directed the GMC authorities to review the progress on fortnight basis and to submit the progress report accordingly.