Close

DC Doda inspected the ongoing work of Oxygen generation plant at GMC Doda* _Directs executing agencies to work in double shifts,set deadline of 30th April for the completion_

Publish Date : 20/04/2021
Doda, April 20:
The Deputy Commissioner (DC) Doda,Vikas Sharma today visited GMC Doda to inspect the ongoing civil work of Oxygen generation plant, besides inspected the functioning of recently installed oxygen manifold system.
 
It has been apprised to the DC that the civil work shall be completed within days, besides the tender of cross over flyover for the supply of oxygen to the manifold has been opened today and shall be expedited.
 
The DC directed the concerned authorities to work in double shifts and to complete  the civil work by or before the 30th of April, besides directed them to allot the work of cross over to the contractor immediately so that it shall be completed vis a vis the OGP.
 
Besides the Ex En Mechanical department apprised the DC that the machinery for oxygen generation plant is on the way and shall reach to Doda within days and shall be installed as soon as OGP hall shall be completed by the PWD department.
 
Regarding establishment of 630 KVA sub station it has been apprised the DC that the work has been re tendered and shall be open by 24th of April.
 
The DC directed to expedite the progress as soon as the bid shall be open and to ask the contractor to mobilise the resources immediately so that the purpose of the project shall met in letter and spirit.
 
The DC said that it is a lifeline project keeping in view the Covid-19 scenario and it should be taken on priority basis for the safety and security of the patients.
 
Among others accompanied the DC are Principal GMC Doda,CMO Doda,Ex En PWD, Mechanical department,MS Associated Hospital GMC Doda,AO GMC Doda besides other concerned officials.