*DDC Doda reviews tendering status of Capex works* _Calls for speed up in tendering process, Directs to avoid unnecessary delays in accord of administrative approval_

Publish Date : 27/09/2021
ddc
Doda, September 25:
District Development Commissioner (DDC) Doda,Vikas Sharma today chaired the meeting of key Officials of various line departments including executing agencies to review the progress of tendering process of Capex works approved under PRI grants.
 
During the meeting the DDC enquired about the number of works which are tendered out of the total appeoved works, number of works alloted and number of works accorded administrative approval.
 
It has been informed to the DDC that out of 1421 works, 867 works have been accorded Adminstrative approval in which 808 stands tendered, in addition to this the DDC has been informed that today two NIT’s having around 107 works are going to open which will be allotted accordingly.
 
Taking strong concern  of the low performance under accord of administrative approval the DDC directed the ACD to expedite the accord process and to complete the process by Monday.
 
While reviewing the department wise tendering status the DDC asked the planning section to seek explaination from the Ex En PHE Gandoh for low performance under tendering of works, besides cautioned the others to tender their pending works in speedy manner so that they shall be allotted timely and execution shall be started on war footing basis.
 
The Ex En PDD informed the DDC that around 75 works handed over to them under PRI grants are not feasible to be taken up, for which the DDC directed the ACD to submit the list to the DC office so that they shall be further submitted to the higher authorities for further course of action.
 
In addition to this the DDC directed the SE JPDCL to expedite the Techinal sanction by mobolising their respective Ex En’s and to accord the administrative approval of all the works for timely completion.
 
While reviewing the pending estimation of PRI grant works the DDC directed the ACD to submit the list of non performing JE’s/TA’s to his office so that strict action shall be ensured against them, besides asked ACD to monitor the progress on daily basis in all manners with regard to PRI grant works.
 
The meeting was attended by SE JPDCL Kishtiwar-Doda, CPO Doda,ACD Doda,AC Panchayats, EX en PDD, EX en REW, EX en PHE Doda & Gandoh, AD Planning DC office, besides AEE’s were also present.