*DDC Doda reviews performance of Jal Shakti, I&FC departments* _Directs for 75 % physical and financial progress by 31st December._ *SE Hydraulics to consider Work audit of the month for release of salary of Engineers/ Officials.*
Publish Date : 20/12/2022
Doda, December 19: District Development Commissioner Doda, Vishesh Paul Mahajan, today chaired a meeting of Officials of Jal Shakti and Irrigation & FC department here in the Conference Hall of DC office complex and reviewed the progress of works approved under JJM and other heads.
Threadbare discussion was held with regard to physical and financial progress of the schemes approved under JJM, District Capex and other heads. He took first hand appraisal of the schemes approved under JJM and their updated status including schemes tendered and alloted for execution on ground.
It was informed that all the 185 schemes under JJM have been tendered out of which in 130 schemes sufficient response to allot the work has been recieved, while till date 98 schemes have been alloted on which work have been started on ground.
DDC directed to book the expenditure immediately in respect of all the completed work. He asked the engineers to use the technology for real-time inspection for quality of works under execution. He instructed them to get the physical and financial progress in JJM and other schemes upto 75% achieved by 31st of December this year.
He has instructed the Planning section to set tangible targets under all the schemes to be achieved by 31st December 2022, 31st January 2023, 28th February 2023 and 31st March 2023. The SE Hydraulics was asked to ensure the adherence to the achievement both physical and financial as per the schedule/ timeline issued by Planning section of DC office. He emphasized on the quality of work while adhering to the timeline. He reteriated that the objective of JJM to provide safe, quality drinking tape water to every household must be achieved in toto.
He asked the Superintending Engineer Hydraulic Doda to consider the work audit and physical and financial progress of engineering and non engineering staff before releasing their monthly salary.
Besides DDC directed the executing officers to expedite the physical and financial progress of the works entrusted to them under different schemes as per the already fixed deadline.
DDC has also instructed the concerned to process for stoping of salary of those engineering and non engineering officials whose progress is poor and who pose casual approach towards their legitimate duties and directions of their higher authorities.
Among others present in the meeting were ADDC Doda, SE Hydraulic, CPO Doda, ACD Doda, Ex Ens of JSD and I&FC, AEEs, AEs, JEs and other concerned officials.