*34 roads with sanctioned length of 354.93 KM of various stages going to be complete by PMGSY in the district during 2020* _DDC directs to expedite the progress and complete all the projects under fixed timeline_
Publish Date : 24/02/2020
DODA, February 19:
District Development Commissioner,Dr Sagar D Doifode convened a meeting with the key officials of PMGSY department and reviewed the financial and physical status of the ongoing projects across the district besides reviewed the bottlenecks if any.
During the meeting DDC in detail reviewed the progress of all ongoing projects across the district in phase and stage manner besides fixed the timelines for the completion of various projects which shall be completed during 2020 in respect of both PIU Doda and Thathri.
Regarding bottlenecks DDC directed the both the Ex En’s to submit the list of projects in phase manner alongwith the name besides to mention that at what level the project is being held up so that the matter will be taken up with the concerned authorities for necessary action.
Regarding Gatha-Dhalwali road land acquisition issue DDC directed the ADC Bhaderwah to take up the matter with the executing agencies and resolve the land issue at earliest for the timely completion of the road, besides directed the ACR Doda to depute one pathwari exclusively for Jangalwar Sarsi road and resolve the land acquisition issue of the respective road at earliest.
Further DDC Doda fixed the responsibility to both the Ex En’s of Doda and Thathri to complete the BT work of 100Km’s in their respective divisions by the end of April 2020 without any fail.
The details of the projects to be completed in 2020 by PIU Doda under various phases and different stages are Jodhpur to parshola part 1(20km),B B Bhagwah Ganika to Kotli(11.575km),Doda Bharath road to Bagla(5km), Kastigarh to Chill via Gagla(14.10km),Saras to Kastigarh (16.32 km),Malhoti to Dugli(5 km),Dali to Kalihand(8.20 km),Doda to Malwana Jagir(13.00km),B B Bhagwah Ganika to Kotli phase ix(11.56km),Bhagwah to Dessa(10.25 km),Chilli to Dhandal(20km),Marsoo to Charote(18.225km),Gangalwar to Sarsi Part ii(3.875km),Gatha to Dhalwali(4.40km),Shiva to Sharerna Kalan(5km),Bhargran to Behota(15km),Bhargran to Rote(13km),Seri to Chatra(6km),Ludna to Gundna(8km), Bharat to Bagla phase X(5km),Malwana Jagir to Abli Masri(6km),Doda Bharath road to Al(6km),Jodhpur to Parshola part (20km),Gangalwar to Sarsi upgradation (4km),Doda to Bhagwah upgradation (14.575km),B B Bhagwah Kastigarh to Chill via Gagla phase xi(14.10km),Pranu to Masri are(10.45km).
Similarly the detail of projects going to complete by PIU Thathri during the current year of various phases and stages are Gandoh to Dhadkaie(5km),Dudhwar to Chanti(6.60km),Balance work of Tantli to Gurekhai part 1(2.60km),Balance work km 60th NH 1B to Snour Thawa(15km),Thathri to Chira(19km),Khara to Tanta (12.13km),Km 76th NH 1B Kandote to Inderella stage 1&2(5.70km).
The meeting was attended by SE PMGSY, CPO Doda,Ex En’s Doda and Thathri, besides by AEE’S/AE’s and JE’s of the executing department.